Distribution Center – Redlands, CA
- NACT
- Jun 19, 2019
- 1 min read
High Traffic Distribution Center – work performed by Garrison Engineered
Type of Repair: Concrete and Joint Repair in a busy distribution center
Outline of Work Performed: Removed 82,300 LF of failing epoxy joint filler and replaced with full-depth rapid-set polyurea joint filler. Installed 120 LF of armored joint.
Products Installed: Polyurea Joint Filler and Epoxy Repair Mortar
Results: Averaged 5,000 lineal feet of removed and replaced joints per night working 10-hour overnight shifts. Required to accommodate the client’s intense operations schedule with over 300 lift trucks running 24-hours per day. New joint filler had to be cured and ready for full lift truck traffic each morning.

Tags: armored joint, case studies, Concrete Repair, construction, Crack Repair, Distribution Center_Joint Repair, work