top of page
Search

Distribution Center – Redlands, CA

  • Writer: NACT
    NACT
  • Jun 19, 2019
  • 1 min read

High Traffic Distribution Center  – work performed by Garrison Engineered

Type of Repair: Concrete and Joint Repair in a busy distribution center

Outline of Work Performed: Removed 82,300 LF of failing epoxy joint filler and replaced with full-depth rapid-set polyurea joint filler.  Installed 120 LF of armored joint.

Products Installed:   Polyurea Joint Filler and Epoxy Repair Mortar

Results:  Averaged 5,000 lineal feet of removed and replaced joints per night working 10-hour overnight shifts.  Required to accommodate the client’s intense operations schedule with over 300 lift trucks running 24-hours per day.  New joint filler had to be cured and ready for full lift truck traffic each morning.



 
 
 